The Department of the Interior and Local Government (DILG) MIMAROPA, through its Project Development and Management Unit (PDMU), inspected and documented projects across various municipalities in the province of Oriental Mindoro on September 15-19, 2025.
The inspection and documentation were led by the OPDS and regional engineers, as well as the project evaluation officers.
The projects inspected were as follows:
– On-site research Services and Facilities related to Agriculture Activities (ON-GOING)
– Multi-Purpose building in Barangay Bayanan, Municipality of Pola (NOT YET STARTED)
– Construction of Multi-Purpose building in Barangay Santo Nino, Naujan (COMPLETED)
– Construction of Multi-Purpose building in Barangay Santa Maria, Naujan (COMPLETED)
– Construction of Multi-Purpose building in Barangay General esco, Naujan (ON-GOING)
– Construction of Water Supply System in Barangay Biga, Calapan City (COMPLETED-FOR SUBMISSION OF DOCUMENTS)
As a result of the inspection, a total of six projects were reviewed. Among them, three have been completed and functional, with one project awaiting the submission of required documents. Two projects are currently on-going, while one project has not yet started.